Sunday - August 23, 2026
Con Edison Completes Major Project to Improve Electric Reliability on Staten Island
March 28, 2024
NEW YORK, March 28 -- Consolidated Edison, a provider of energy-related products and services, issued the following news release:

Con Edison has completed a $200 million construction project that will increase electric service reliability in several neighborhoods on the east side of Staten Island.

The two new 138,000-volt, underground cables - also called feeders - run 4.6 miles across the island, from a substation in Travis on the west side to a substation on Dongan Hi . . .

Targeted News Service Document Request Form

This document is available to you by e-mail if you complete the form below with relevant information. There may be a fee for this article or ongoing service of similar materials. We will be in touch shortly.

Click here for more information about our products