Wednesday - September 16, 2026
Fla. PSC Adjusts DEF's Replacement Fuel Cost Recovery Request for CR4 Outage
December 08, 2021
TALLAHASSEE, Florida, Dec. 8 -- The Florida Public Service Commission issued the following news release on Dec. 7, 2021:

The Florida Public Service Commission (PSC) today ordered Duke Energy Florida, LLC (DEF) to credit customers $7.2 million for replacement power costs caused by its forced outage at Crystal River Unit 4 (CR4).

A forced outage of CR4 was necessary from January 2021 through April 2021 after the plant operator's three attempts to synchronize the unit . . .

Targeted News Service Document Request Form

This document is available to you by e-mail if you complete the form below with relevant information. There may be a fee for this article or ongoing service of similar materials. We will be in touch shortly.

Click here for more information about our products