TALLAHASSEE, Florida, Dec. 8 -- The Florida Public Service Commission issued the following news release on Dec. 7, 2021:
The Florida Public Service Commission (PSC) today ordered Duke Energy Florida, LLC (DEF) to credit customers $7.2 million for replacement power costs caused by its forced outage at Crystal River Unit 4 (CR4).
A forced outage of CR4 was necessary from January 2021 through April 2021 after the plant operator's three attempts to synchronize the unit . . .
The Florida Public Service Commission (PSC) today ordered Duke Energy Florida, LLC (DEF) to credit customers $7.2 million for replacement power costs caused by its forced outage at Crystal River Unit 4 (CR4).